Refurbishment of Refinitiv (Formerly as Thomson Reuters) YCK 1/F Data Centre, Shatin, H.K.
Since 2014, we have been appointed by Thomson Reuters to conduct a series of projects for the improvement of the mechanical and electrical systems of the data center in Shatin. The Data Centre is with total floor area of 1,500m2. This project is to refurbish the current data centre on 1/F and upgrade/ modify the mechanical and electrical systems for the future expansion. The upgrading works cover most major M&E systems in the data center including Power Distribution Unit, Isolation Transformer, Precision CRAC Unit, Cold Aisle Containment, Pre-action Fire Sprinkler System and FM-200 Fire Suppression System.
 Feasibility Study on Data Centre at Fongs Building, Tsing Yi, Hong Kong
Fongs Building is a 8-storey industrial building. Feasibility study was carried out to convert the building into a data centre up to Tier III standard. Mission critical M&E plants including generators, chiller plants, UPS system, fuel oil system and H.V. power system are to be designed to support the data centre.
 Thomson Reuters Data Centre, Shatin, H.K.
Since 2014, we have been appointed by Thomson Reuters to conduct a series of projects for the improvement of the mechanical and electrical systems of the data center in Shatin. The Data Centre is with total floor area of 1,500m2. Our scope of works includes upgrading / replacement feasibility studies, design and project management. The targets of the work are to enhance the data center overall energy efficiency and alleviate any possible system risk. These projects cover most major M&E systems in a data center including Power Distribution Unit, Uninterrupted Power Supply Unit, Isolation Transformer, Precision CRAC Unit, Chiller Plant, Cold Aisle Containment, Pre-action Fire Sprinkler System and Building Management System.
 Special Waiver Application for Data Centre, Fanling, Hong Kong
The scope of services include preliminary designs of M&E plants for special waiver application for conversion of existing building into data centre.

 New Chiller Installation for Equinix HK3 Data Centre, Tsuen Wan, H.K.
We are engaged as M&E consultant for a new chiller installation of Equinix’s data centre at Tsuen Wan - “HK3 Data Centre”. The project comprises installation of a new chiller, the modification of existing plant control system and Building Management System BMS to suit the operation of the new chiller. Talent carries out M&E design and project administration for the project.

 Thomson Reuters Data Centre Phase 2 and Chiller Plant Replacement at Shatin, H.K.
Following the engagement of the M&E design for Thomson Reuters Data Centre Phase 1 at Yuen Chau Kwok, we are engaged again for the Phase 2 project together with the Chiller Plant Replacement. The Data Centre is with total floor area of 1,500m2. The project comprises the replacement of chiller plant, the upgrading of CRAC units, the modification of electrical system and fire services installation.
 AIS Data Center, Chonburi, Thailand
Following the engagement for the M&E design verification services for COL Data Centre in HK by Huawei Tech. Investment Co. Ltd, we commissioned again for the AIS Data Centre project in Thailand. This is the first Data Centre project we work in Thailand. We hope that there would be more chance to participate in Data Centre project in the South East Asia in the near future. The single storey data centre is with floor area around 1,700m2 and designed to tier III standard. Mission critical facilities are provided including new generators, chiller plants and UPS system. Talent carried out quality assurance service for this project.

 COL Data Centre at 18/F, Cable TV Tower, 9 Hoi Shing Road, Tsuen Wan, H.K.
The data centre consists of 1 storey of equipment area with floor area 1,700m2. Mission critical facilities of Tier III standard are provided including new generators, chiller plants and UPS supply. Talent is responsible for design and project administration and T&C of the M&E Services & IST.

 Cargo Consolidation Complex Data Centre for PCCW Solution, Kwai Chung, Hong Kong
The data centre consists of 9-storeyed equipment area with floor area around 12,600 m2 and is designed to tier III standard. Mission critical facilities are provided including new high voltage system, transformers, generators, chiller plants and UPS system. Talent carries out design, project administration for the project together with the upgrading of infrastructure for the centre.

 Citic Telecom International Data Centre, Hong Kong
Following the successful inauguration of the Citic Telecom International Data Centre at Kwai Chung, we are engaged in another Data Centre for Citic Telecom International. The new data centre with Tier 3 provisions occupies an area of 2,300m2, and will be equipped with completely independent mission critical facilities, mechanical and electrical plants. Engaging in the data centre project with same design team & project management team will definitely improve the work accuracy and efficiency.
 Data Centre for PCCW Powerbase at KSG Exchange, H.K.
The data centre consists of 4 storey of equipment area with floor area around 7,050m2. Mission critical facilities of Tier III standard are provided including new transformers, generators, chiller plants and UPS supply.

 IBM Office at PCCW Tower, Quarry Bay, H.K.
Portion of the existing IBM office located at several floors of PCCW Tower is renovated to cope with operation needs. Total renovated area is around 1,000m2. Talent carries out design and project administration of fitting out for existing offices and improvement of the M&E design on existing Solution Centre.

 Data Centre for PCCW FTN Exchange, H.K.
After completing several data centre projects for a telecom service company, we have been commissioned again for the data centre from the same client. The data centre consists of 2 storeys of equipment area. Total area is about 2,300m2. Mission critical facilities are provided including new transformers, generators, chiller plants and UPS system. Talent carries out design, project administration and upgrading of infrastructure for the centre.
 Data Centre for Citic 1616 in Kwai Chung, H.K.
The data centre includes 2 storey equipment area of 2,400m2, 1 storey NOC and supporting area of 1,200m2. Mission critical facilities are provided for the data centre of Tier III requirement with computer room air conditioning, precision power supply, UPS and generator back up. Talent is responsible for design and project administration of the M&E services.

 Infrastructure for Tai Po Exchange Building, Tai Po, H.K.
The building houses telecom equipment and needs upgrading to increase their capacities. Works include the addition of transformer and associated switchgears, upgrading of generators and addition of chillers. Spaces are allowed in the design for further upgrading in the future.

 Data Centres at Fo Tan, Shatin, H.K.
Talent is engaged as an M&E design checker together with testing & commissioning consultant including integrated system test. The data centre is operated by IBM with total floor area of 1,300m2 including BRC office. Mission critical facilities are provided for these data centres with computer room air conditioning, precision power supply, UPS and generator backup.

 Data Centres at Science City, Guangzhou, China
Talent is engaged as an M&E design checker together with testing & commissioning consultant. The data centre is operated by PCCW with total floor area of 1,650m2. Mission critical facilities are provided for these data centres with computer room air conditioning, precision power supply, UPS and generator backup.

 Nokia New Office and R&D Center at Binjiang, Hangzhou, China
Scope of service includes design and project administration of the M&E installations for the fitting-out works. The project is 12,000m2 including office, R&D labs and server rooms. The M&E design is developed based on the building existing provisions to suit the Nokia’s requirements.

 IT Facilities for Royal Bank of Scotland, AIG Tower, Central, H.K.
The M&E consultancy is for the IT facilities for the Royal Bank of Scotland located on 26/F to 29/F of the AIG Tower. The total floor area of the premises is around 4,000m2 comprising computer room and general office.
 IBM BICC TSS Expansion, Beijing, China
The project includes the expansion of an IT research lab of 600m2 and the renovation of part of the existing office area of 300m2 to IT supporting area comprising testing labs and training rooms.

 Whirlpool R&D Centre, Shenzhen, China
Whirlpool R&D Centre in Shenzhen comprises research, design and product laboratories together with offices with total area of 4,000m2. Transformer was added to support the centre as regular power source was insufficient. The project was completed in May 2006.
 Bell Labs & Research Centre of Lucent Technologies at WangJing, Beijing, China
Full M & E consultancy and project administration for IT research labs and office areas in a 6-storey building with a total floor area of 12,000m2. The M & E design including incoming power upgrade, addition of 24 hours air-conditioning system and UPS dual power supply for IT equipment rooms.
 IBM CSDL Expansion Project at Powercreative, Beijing, China
Full M & E consultancy and project administration for the computer research centre with floor area of 4,000m2 including modification of existing M & E provisions, addition of 24 hours air-conditioning for IT equipment rooms, fresh air heat exchangers for labs, ELV and BMS.
 IBM Call Centre at Shenzhen, China
The call centre is a computerized customer support centre with 380 work stations. Total area of the centre is around 2,650m2.

 IBM Research Centre at Shengdi, China
The scope of consultancy service for the computer research centre includes the full M & E design and project administration including CRAC and specialist computer cabling for 2 storeys facilities with total area of 4,200m2.

 CNC Data Centre at Beijing, PRC
The data centre consists of data storage, network exchange centre and NOC with total floor area of around 5,000m2. The NOC was the largest one in Asia at the time of completion.


 Dynergy Data Centre at Beijing, PRC
The data centre consists of data storage and call centre together with NOC with total floor area of around 2,300m2.


 Computer Room for TWGHs at Wong Fung Ling Memorial Building
The main computer room of the Tung Wah Group of Hospitals suffered from poor environmental control and high energy cost. The scope of consultancy is to redesign the existing A/C system to achieve close environmental control and energy efficiency.
 Reuter’s Computer Centre at Cityplaza 3, H.K.
The scope of consultancy comprises the design of close control air conditioning system, fire fighting system, electrical and auxiliary systems and project administration work.
 
 